FINDING OF NO SIGNIFICANT IMPACT
FALL CREEK DAM AND RESERVOIR ADULT FISH FACILITY UPGRADE
LANE COUNTY, OREGON

I find that the selected course of action to upgrade the existing adult fish collection facility at Fall Creek dam and reservoir will not significantly affect the quality of the human environment, and that an Environmental Impact Statement is not required. The selected course of action is the Preferred Alternative as described in the Environmental Assessment - Fall Creek Dam and Reservoir Adult Fish Facility Upgrade (U.S. Army Corps of Engineers, January 2015) (herein referred to as the EA) ...

JOSE L. AGUILAR
COL, EN
Commanding

26 Feb 15