Portland District

Home
Home > Missions > Regulatory > Notices

Public Notices by Year

1 ... 6 7 8 9 10 11 12 13 14 15 ... 27

FILTER:
permit application




NWP-2016-517 - 12/21/2016: Michael LaDouceur is the Regulatory point-of-contact for this permit application from DuPont Fabros Technology to conduct work impacting a tributary to Waible Creek and wetlands Hillsboro, Oregon.
Expiration date: 1/16/2017


NWP-2016-92 - 12/13/2016: Michael LaDouceur is the Regulatory point-of-contact for this permit application from Nike, Inc. to conduct work impacting two wetlands on the Nike World Headquarters campus in Beaverton, Washington County, Oregon.
Expiration date: 1/12/2017


NWP-2016-455 - 12/13/2016: Tyler Krug is the Regulatory point-of-contact for this permit application from Billy Wright and Richard Todd to conduct work impacting the Pacific Ocean near Gold Beach and Brookings, Curry County, Oregon.
Expiration date: 1/7/2017


NWP-2016-547 - 12/7/2016: Andrea Wagner is the Regulatory point-of-contact for this permit application from David and Laurie Dukes to conduct work impacting wetlands adjacent to Crooks Creek in Millersburg, Linn County, Oregon.
Expiration date: 1/4/2017


NWP-2015-402 (Revised) - 11/22/2016: Judy Linton is the Regulatory point-of-contact for this proposal to change the northern boundary of the proposed Regional General Permit from the Umpqua River to the Siuslaw River. The proposed RGP would authorize certain maintenance activities in waters of the U.S. within Douglas, Coos, Curry and Lane counties from the Siuslaw River in Lane County to the California border and within the limits of Oregon’s designated coastal zone.
Expiration date: 12/7/2016

ATTACHMENTS:  


NWP-2016-313 - 11/10/2016: Omar Ortiz is the Regulatory point-of-contact for this permit application from Parkway West, LLC to conduct work impacting wetlands adjacent to Amazon Creek in Eugene, Lane County, Oregon.
Expiration date: 12/6/2016


NWP-2013-83/1 - 10/21/2016: Anita Andazola is the Regulatory point-of-contact for this permit application from the Bend Park and Recreation District to conduct work impacting the Deschutes River below the Colorado Street Dam, in the city of Bend, Deschutes County, Oregon.
Expiration date: 11/7/2016


NWP-2003-602-1 - 10/21/2016: Danielle Erb is the Regulatory point-of-contact for this permit application from Port District No. One of Wahkiakum County to conduct work impacting the Elochoman Slough and Marina a side channel of the Columbia River in Cathlamet, Wahkiakum County, Washington.
Expiration date: 11/20/2016


NWP-2005-430/3 - 10/19/2016: Teena Monical is the Regulatory point-of-contact for this permit application from Hayden Homes, LLC to conduct work impacting unnamed tributaries to the Long Tom River and adjacent and abutting wetlands in Veneta, Lane County, Oregon.
Expiration date: 11/17/2016


NWP-2005-713-5 - 10/19/2016: Danielle Erb is the Regulatory point-of-contact for this permit application from St. Helens Marina, LLC to conduct work impacting the Columbia River in St. Helens, Columbia County, Oregon.
Expiration date: 11/17/2016


1 ... 6 7 8 9 10 11 12 13 14 15 ... 27

NWP-2018-285

Brad Johnson is the Regulatory point-of-contact for this permit application from Hix Snedeker Development, LLC to conduct work impacting waters of the United States in Molalla, Clackamas County, Ore.
5 days ago

NWP-2018-33

Danielle Erb is the Regulatory point-of-contact for this permit application from Airpark Development, LLC to conduct work impacting wetlands in Scappoose, Columbia County, Ore.
12 days ago

NWP-2013-32-1

Brad Johnson is the Regulatory point-of-contact for this permit application from Lake Side Industries, Inc. to conduct work impacting waters of the United States in Portland, Multnomah, Ore.
13 days ago

NWP-2018-296

Danielle Erb is the Regulatory point-of-contact for this permit application from S Cullen, LLC to conduct work impacting waters of the United States in Astoria, Clatsop County, Ore.
13 days ago

NWP-2013-227-3

Melody White is the Regulatory point-of-contact for this permit application from Dean Dordevic to conduct work impacting the Willamette River and Ross Island Lagoon in Portland, Multnomah County, Oregon.
15 days ago

NWP-1997-114-2

Melody White is the Regulatory point-of-contact for this permit application from Ash Grove Cement Company to conduct work impacting waters of the United States in Portland, Multnomah County, Ore.
15 days ago

NWP-2018-298

Benny A. Dean Jr. is the Regulatory point-of-contact for this permit application from Northernwood, LLC. to conduct work impacting waters of the United States in Philomath, Benton County, Ore.
16 days ago

NWP-2007-196-2

Tyler Krug is the Regulatory point-of-contact for this permit application from Tidewater Contractors to conduct work impacting the Chetco River at river mile 10.2 in Brookings, Curry County, Oregon.
33 days ago

NWP-2015-83-1

Kinsey M. Friesen is the Regulatory point-of-contact for this permit application from MIGAR Corporation to conduct work impacting wetlands in Monmouth, Polk County, Ore.
37 days ago

NWP-2018-117

Brad Johnson is the Regulatory point-of-contact for this permit application from Athey Creek Christian Fellowship to conduct work impacting wetlands in West Linn, Clackamas County, Oregon.
47 days ago

NWP 2018-190

Margaret Chang is the Regulatory point-of-contact for this permit application from the Port of Kalama to conduct work impacting the Columbia River at the Port of Kalama in Cowlitz County, Washington.
47 days ago

NWP-1998-165-4

Andrea Wagner is the Regulatory point-of-contact for this permit application from Grants Pass Jetboats, Inc. to conduct work impacting the Rogue River from river mile 84-101 in Grants Pass, Josephine County, Oregon.
48 days ago

NWP-2016-495

Winston Zack is the Regulatory point-of-contact for this permit application from Lennar Northwest to conduct work impacting waters of the United States in Milwaukie, Clackamas County, Ore.
54 days ago

NWP-2017-41

Mr. Tyler Krug is the Regulatory point-of-contact for this permit application from Jordan Cove Liquefied Natural Gas to conduct work impacting waters of the United States and the alteration of federally-authorized projects.
57 days ago

NWP-2017-262/1

Ms. Kinsey Friesen is the Regulatory point-of-contact for this permit application from West Hills Land Development, LLC to conduct work impacting wetlands in Beaverton, Washington County, Ore.
65 days ago

NWP-2018-161

Melanie O'Meara is the Regulatory point-of-contact for this permit application from Hayden Homes to conduct work impacting a pond and wetlands in Springfield, Lane County, Oregon.
72 days ago

NWP-2006-927/2

Tyler J. Krug is the Regulatory point-of-contact for this permit application from Freeman Rock, Inc. to conduct work impacting wetlands in Brookings, Curry County, Ore.
75 days ago

NWP-2018-122

Andrea Wagner is the Regulatory point-of-contact for this permit application from ECM Brandis, LLC to conduct work impacting wetlands and a tributary in Albany, Linn County, Oregon.
82 days ago

NWP-2018-142

Danielle Erb is the Regulatory point-of-contact for this permit application from Seaside School District to conduct work impacting streams and wetlands in Seaside, Clatsop County, Oregon.
89 days ago

NWP-2018-57

Kinsey Friesen is the Regulatory point-of-contact for this permit application from Monmouth Power and Light Utility to conduct work impacting wetlands in Monmouth, Polk County, Ore.
96 days ago

NWP-2000-983-1

Melody White is the Regulatory point-of-contact for this permit application from MC Marina, LLC to conduct work impacting the Columbia River at river mile 108.5 in Portland, Multnomah County, Ore.
104 days ago

NWP-2018-116

Kinsey Friesen is the Regulatory point-of-contact for this permit application from Dallas Maple Street, LLC to conduct work impacting a wetland and tributary of Rickreall Creek in Dallas, Polk County, Ore.
104 days ago

NWP-2017-262

Kinsey Friesen is the Regulatory point-of-contact for this permit application from West Hills Land Development, LLC to conduct work impacting wetlands, tributaries and a drainage channel in Beaverton, Washington County, Ore.
113 days ago

NWP-1994-462-1

Margaret Chang is the Regulatory point-of-contact for this permit application from the Port of Kalama to conduct work impacting the Columbia River in Columbia County, Oregon and Cowlitz County, Washington.
113 days ago

NWP-2018-50

Andrea Wagner is the Regulatory point-of-contact for this permit application from Greater Albany Public Schools to conduct work impacting wetlands in Albany, Linn County, Ore.
121 days ago

NWP-2010-141-4

Melody White is the Regulatory point-of-contact for this permit application from Columbia Crossings to conduct work impacting the Columbia River at river mile 106 in Portland, Multnomah County, Ore.
125 days ago

NWP-2006-946-2

Melody White is the Regulatory point-of-contact for this permit application from TLP Management Services, LLC to conduct work impacting the Willamette River at River Mile 4.9 in Portland, Multnomah County, Ore.
126 days ago

NWP-2018-93

Melanie O'Meara is the Regulatory point-of-contact for this permit application from the Eugene Civic Alliance to conduct work impacting wetlands in Eugene, Lane County, Ore.
126 days ago

NWP-2017-142

Melanie O'Meara is the Regulatory point-of-contact for this permit application from U.S. Forest Service to conduct work impacting the South Fork McKenzie River, tributaries, wetlands and ponds in McKenzie Bridge, Lane County, Ore.
127 days ago

NWP-2018-37

Melanie O'Meara is the Regulatory point-of-contact for this permit application from U.S. Forest Service to conduct work impacting the Cougar Reservoir in McKenzie Bridge, Lane County, Ore.
127 days ago

NWP-1997-910-5

Melody White is the Regulatory point-of-contact for this permit application from the Portland Yacht Club to conduct work impacting the Columbia River in Corvallis, Benton County, Ore.
138 days ago

NWP-2017-500

Brian Zabel is the Regulatory point-of-contact for this permit application from Oregon State University, Design and Construction to conduct work impacting wetlands in Newport, Lincoln County, Ore.
154 days ago

NWP-2014-411

Brad A. Johnson is the Regulatory point-of-contact for this permit application from Rare Earth Resources, LLC to conduct work impacting wetlands in Halfway, Baker County, Ore.
160 days ago

NWP-2015-436

Benny A. Dean Jr. is the Regulatory point-of-contact for this permit application from Pacific Power to conduct work impacting wetlands in Grants Pass in Josephine County, Ore. and White City in Jackson County, Ore.
167 days ago

NWP-2015-502/1

Andrea Wagner is the Regulatory point-of-contact for this permit application from MBBH Development, LLC to conduct work impacting wetlands in Albany, Linn County, Ore.
181 days ago

NWP-2017-88

Kinsey Friesen is the Regulatory point-of-contact for this permit application from Polygon WLH LLC., to conduct work impacting two ponds and four wetlands in North Bethany, Washington County, Ore.
181 days ago

NWP-2017-465

Benny A. Dean Jr. is the Regulatory point-of-contact for this permit application from City of Corvallis to conduct work impacting wetlands in Corvallis, Benton County, Ore.
189 days ago

NWP-2017-56-1

Andrea Wagner is the Regulatory point-of-contact for this permit application from Glorietta Bay, LLC to conduct work impacting wetlands in Albany, Linn County, Ore.
189 days ago

NWP-2017-450

Andrea Wagner is the Regulatory point-of-contact for this permit application from Greater Albany School District to conduct work impacting wetlands in Albany, Linn County, Ore.
190 days ago

NWP-2016-335

Tyler Krug is the Regulatory point-of-contact for this permit application from the Daniel Graham to conduct work impacting Coos Bay and wetlands abutting and adjacent to Coos Bay in Coos Bay, Ore.
201 days ago

NWP-2017-292 (Correction)

Benny A. Dean Jr. is the Regulatory point-of-contact for this permit application from Snyder Creek Development, LLC. to conduct work impacting wetlands, open water and drainage ditches in Eagle Point, Jackson County, Ore.
209 days ago

NWP-1999-1245-4

Danielle Erb is the Regulatory point-of-contact for this permit application from United States Gypsum Company to conduct work impacting the Columbia River at river mile 65.5 in Rainier, Columbia County, Ore.
212 days ago

NWP-2017-29

Michael LaDouceur is the Regulatory point-of-contact for this permit application from Portland General Electric to conduct work impacting a wetland, which drains into Rock Creek via an unnamed tributary in Hillsboro, Washington County, Ore.
212 days ago

NWP-2014-72-2

Melanie O'Meara is the Regulatory point-of-contact for this permit application from Eugene Water and Electric Board to conduct work impacting the McKenzie River, abutting wetlands and hydroelectric canals in Leaburg, Lane County, Ore.
222 days ago

NWP-2017-414

Brad Johnson is the Regulatory point-of-contact for this permit application from St. Hilaire Brothers Hermiston Farm, LLC. to conduct work impacting the Columbia River at mile 301.7 in Hermiston, Umatilla County, Ore.
238 days ago

NWP-2017-345

Brad Johnson is the Regulatory point-of-contact for this permit application from South Prairie Drainage District to conduct work impacting the Tillamook River and Anderson Creek in Tillamook, Tillamook County, Ore.
238 days ago

NWP-2017-292

Benny A. Dean Jr. is the Regulatory point-of-contact for this permit application from Snyder Creek Development, LLC. to conduct work impacting wetlands, open water and drainage ditches in Eagle Point, Jackson County, Ore.
238 days ago

NWP-2007-916-2

Margaret Chang is the Regulatory point-of-contact for this permit application from the Port of Vancouver to conduct work impacting the Columbia River in Vancouver, Clark County,
244 days ago

NWP-2006-844-1

Andrea Wagner is the Regulatory point-of-contact for this permit application from the Marion County Public Works to conduct work impacting the Willamette River at river mile 106.5 in Buena Vista, Polk and Marion counties, Ore.
244 days ago

NWP-2017-201-1

Anita Andazola is the Regulatory point-of-contact for this permit application from the City of Sutherlin to conduct work impacting 1.27 acres of wetland and 430 linear feet of a tributary of Cook Creek in Sutherlin, Douglas County, Ore.
245 days ago

NWP-2017-252

Benny Dean is the Regulatory point-of-contact for this permit application from Mountain West Investments to conduct work impacting wetlands located in Philomath, Oregon.
264 days ago

NWP-2015-41

Michael LaDouceur is the Regulatory point-of-contact for this permit application from the Tualatin Valley Water District and the City of Hillsboro to conduct work impacting the Willamette River, the Tualatin River and several of its tributaries, multiple wetlands, and ditches in the cities of Wilsonville, Sherwood, Beaverton, Tigard, Tualatin, and Hillsboro, in Clackamas and Washington Counties, Oregon.
275 days ago

NWP-1994-462-1

Margaret Chang is the Regulatory point-of-contact for this permit application from the Port of Kalama to conduct work impacting the Columbia River at river mile 76 in Kalama, Cowlitz County, Washington and river mile 77.5 in Columbia County, Oregon.
278 days ago

NWP-2017-322

Benny Dean is the Regulatory point-of-contact for this permit application from Gary and Julie Rodgers to conduct work impacting 3.93 acres of wetlands in Albany, Oregon.
285 days ago

NWP-2000-39-3

Margaret Chang is the Regulatory point-of-contact for this permit application from the Port of Longview, Washington, to conduct work impacting the Columbia River near river mile 62, in Columbia County, Oregon.
320 days ago

NWP-2017-280

Brad Johnson is the Regulatory point-of-contact for this permit application from Columbia Improvement District to conduct work impacting the Columbia River at river mile 271.5 in Boardman, Morrow County, Ore.
329 days ago

NWP-2014-408-1

Melody White is the Regulatory point-of-contact for this permit application from 4430 Building, LLC. to conduct work impacting the Willamette River in Portland, Multnomah County, Ore.
341 days ago

NWP-2017-230

Danielle Erb is the Regulatory point-of-contact for this permit application from Big Beams, LLC, to conduct work impacting wetlands in Warrenton, Clatsop County, Oregon.
342 days ago

NWP-2009-565-1

Danielle Erb is the Regulatory point-of-contact for this permit application from the Port of Astoria to conduct work impacting the Columbia River, River Mile 13.5, in Astoria, Clatsop County, Oregon.
345 days ago

NWP-2017-156

Kinsey Friesen is the Regulatory point-of-contact for this permit application from the City of McMinnville to conduct work impacting wetlands, streams and roadside ditches in McMinnville, Yamhill County, Ore.
350 days ago

NWP-2017-71

Michael LaDouceur is the Regulatory point-of-contact for this permit application from CSC Cap Holding, LLC to conduct work impacting four (4) wetlands in Tigard, Washington County, Oregon.
354 days ago

NWP-2016-556

Danielle Erb is the Regulatory point-of-contact for this permit application from Columbia Crossing, LLC to conduct work impacting two (2) wetlands in Rainier, Columbia County, Oregon.
355 days ago

NWP-2016-261

Andrea Wagner is the Regulatory point-of-contact for this permit application from the City of Albany to conduct work impacting five (5) wetlands and the Burkhart Creek Overflow tributary in Albany, Linn County, Oregon.
362 days ago

NWP-2017-283

Melanie O'Meara is the Regulatory point-of-contact for this permit application from the Murphy Company to conduct work impacting three (3) wetlands in Eugene, Lane County, Oregon.
1 years 7 days ago

NWP-2017-243

Benny Dean is the Regulatory point-of-contact for this permit application from Chris Kiilsgaard to conduct work impacting wetlands located in Corvallis, Oregon.
1 years 11 days ago

NWP-2017-253

Melanie O'Meara is the Regulatory point-of-contact for this permit application from Hayden Homes, LLC to conduct work impacting six (6) unnamed wetlands referred to as Wetlands A,B,C,D,E and F in Springfield, Lane County, Oregon.
1 years 22 days ago

NWP-2007-135/1

Tyler Krug is the Regulatory point-of-contact for this permit application from the U.S. Coast Guard to conduct work impacting the Rogue River in Gold Beach, Curry County, Oregon.
1 years 29 days ago

NWP-2017-199

Melanie O'Meara is the Regulatory point-of-contact for this permit application from the Hayden Homes, LLC to conduct work impacting three (3) palustrine emergent wetlands in Springfield, Lane County, Oregon.
1 years 29 days ago

NWP-2016-612

Andrea Wagner is the Regulatory point-of-contact for this permit application from Alan Kay Properties, LLC to conduct work impacting seven wetlands and two tributaries to the Willamette River in Harrisburg, Linn County, Oregon.
1 years 46 days ago

NWP-2007-729-3

Danielle Erb is the Regulatory point-of-contact for this permit application from Warrenton Fiber Company to conduct work impacting the Columbia River at River Mile 10.2 in Warrenton, Clatsop County, Oregon.
1 years 46 days ago

NWP-2016-549

Carrie Bond is the Regulatory point-of-contact for this permit application from the Oregon Department of Transportation to conduct work impacting an unnamed tributary to the Minam River in Union County, Elgin, Oregon.
1 years 55 days ago

NWP-2017-127

Michael LaDouceur is the Regulatory point-of-contact for this permit application from Amberglen South Development Company, LLC to conduct work impacting 5 wetlands referred to as Wetlands A, B, C, D, and E in Hillsboro, Washington County, Oregon.
1 years 57 days ago

NWP-2017-160

Andrea Wagner is the Regulatory point-of-contact for this permit application from the Linn County Road Department to conduct work impacting 3 wetlands and 16 roadside drainages which are tributaries of the Calapooia and Willamette Rivers in Albany, Linn County, Oregon.
1 years 60 days ago

NWP-2017-20

Andrea Wagner is the Regulatory point-of-contact for this proposal to establish a wetland mitigation project in Douglas County, OR.
1 years 74 days ago

NWP-2008-627-1

Kinsey Friesen is the Regulatory point-of-contact for this permit application from Flowers Enterprises, Inc. to conduct work impacting two wetlands in Aurora, Marion County, OR.
1 years 74 days ago

NWP-2008-192-1

Kinsey Friesen is the Regulatory point-of-contact for this permit application from Gramor Investments to conduct work impacting a tributary to Springbrook Creek and four wetlands in Newberg, Yamhill County, OR.
1 years 74 days ago

NWP-2008-00086/2

Benny Dean, Jr. is the Regulatory point-of-contact for this permit application from Applegate Holdings, LLC., to conduct work impacting the Dunawi Creek, two unnamed tributaries and abutting wetlands in Corvallis, Benton County, Oregon.
1 years 84 days ago

NWP-2013-338/2

Melody White is the Regulatory point-of-contact for this permit application from Portland General Electric to conduct work impacting wetlands adjacent to the Willamette River at 12500 NW Marina Way in Portland, Multnomah, OR.
1 years 105 days ago

NWP-2013-233/1

Margaret Chang is the Regulatory point-of-contact for this permit application from the Port of Portland to conduct work impacting four wetlands in Portland, Multnomah County, OR.
1 years 126 days ago

NWP-2016-300

Benny A. Dean Jr. is the Regulatory point-of-contact for this permit application from the City of Medford to conduct work impacting Upton Slough in Medford, Jackson County, Oregon.
1 years 144 days ago

NWP-2016-297

Benny A. Dean Jr. is the Regulatory point-of-contact for this permit application from the City of Medford to conduct work impacting Lone Pine Creek in Medford, Jackson County, Oregon.
1 years 144 days ago

NWP-2017-53

Brad A. Johnson is the Regulatory point-of-contact for this permit application from Riverside Homes, LLC to conduct work impacting two wetlands adjacent to Fanno Creek in Tigard, Washington County, Oregon.
1 years 144 days ago

NWP-2017-54

Andrea Wagner is the Regulatory point-of-contact for this permit application from Glorietta Bay, LLC to conduct work impacting a headwater tributary for Little Oak Creek and abutting wetlands in Lebanon, Linn County, Oregon.
1 years 144 days ago

NWP-2017-00049

Benny Dean is the Regulatory point-of-contact for this permit application from J.Conser and Sons, LLC, to conduct work impacting wetlands located in Philomath, Oregon.
1 years 161 days ago

NWP-2005-713-5

Danielle Erb is the Regulatory point-of-contact for this permit application from St. Helens Marina, LLC to conduct work impacting the Columbia River in St. Helens, Columbia County, OR.
1 years 169 days ago

NWP-2016-616

Margaret Chang is the Regulatory point-of-contact for this permit application from the Port of Portland to conduct work impacting the Willamette River at Terminal 4.
1 years 174 days ago

NWP-2007-5/2

Tyler Krug is the Regulatory point-of-contact for this permit application from Oregon International Port of Coos Bay to conduct work impacting miles 5.5 through 15.0 of Coos Bay and the Pacific Ocean in Empire, Coos County, Oregon.
1 years 174 days ago

NWP-2014-477

Tom Taylor is the Regulatory point-of-contact for this proposal establish a wetland mitigation project in Multnomah County, Oregon.
1 years 202 days ago

NWP-2006-856-1

Kinsey Friesen is the Regulatory point-of-contact for this permit application from Big Eddy Marina Inc., to conduct work impacting the Columbia River (river mile 118), in Portland, Oregon.
1 years 202 days ago

NWP-2004-716-4

Benny Dean Jr. is the Regulatory point-of-contact for this permit application from Corvallis Station LLC to conduct work impacting wetlands adjacent to an unnamed tributary of the Willamette River in Corvallis, Oregon.
1 years 209 days ago

NWP-2016-517

Michael LaDouceur is the Regulatory point-of-contact for this permit application from DuPont Fabros Technology to conduct work impacting a tributary to Waible Creek and wetlands Hillsboro, Oregon.
1 years 209 days ago

NWP-2016-92

Michael LaDouceur is the Regulatory point-of-contact for this permit application from Nike, Inc. to conduct work impacting two wetlands on the Nike World Headquarters campus in Beaverton, Washington County, Oregon.
1 years 217 days ago

NWP-2016-455

Tyler Krug is the Regulatory point-of-contact for this permit application from Billy Wright and Richard Todd to conduct work impacting the Pacific Ocean near Gold Beach and Brookings, Curry County, Oregon.
1 years 217 days ago

NWP-2016-547

Andrea Wagner is the Regulatory point-of-contact for this permit application from David and Laurie Dukes to conduct work impacting wetlands adjacent to Crooks Creek in Millersburg, Linn County, Oregon.
1 years 223 days ago

NWP-2015-402 (Revised)

Judy Linton is the Regulatory point-of-contact for this proposal to change the northern boundary of the proposed Regional General Permit from the Umpqua River to the Siuslaw River. The proposed RGP would authorize certain maintenance activities in waters of the U.S. within Douglas, Coos, Curry and Lane counties from the Siuslaw River in Lane County to the California border and within the limits of Oregon’s designated coastal zone.
1 years 238 days ago

NWP-2016-313

Omar Ortiz is the Regulatory point-of-contact for this permit application from Parkway West, LLC to conduct work impacting wetlands adjacent to Amazon Creek in Eugene, Lane County, Oregon.
1 years 250 days ago

NWP-2013-83/1

Anita Andazola is the Regulatory point-of-contact for this permit application from the Bend Park and Recreation District to conduct work impacting the Deschutes River below the Colorado Street Dam, in the city of Bend, Deschutes County, Oregon.
1 years 269 days ago

NWP-2003-602-1

Danielle Erb is the Regulatory point-of-contact for this permit application from Port District No. One of Wahkiakum County to conduct work impacting the Elochoman Slough and Marina a side channel of the Columbia River in Cathlamet, Wahkiakum County, Washington.
1 years 270 days ago

NWP-2005-430/3

Teena Monical is the Regulatory point-of-contact for this permit application from Hayden Homes, LLC to conduct work impacting unnamed tributaries to the Long Tom River and adjacent and abutting wetlands in Veneta, Lane County, Oregon.
1 years 272 days ago

NWP-2005-713-5

Danielle Erb is the Regulatory point-of-contact for this permit application from St. Helens Marina, LLC to conduct work impacting the Columbia River in St. Helens, Columbia County, Oregon.
1 years 272 days ago

NWP-2016-199

Margaret Chang is the Regulatory point-of-contact for this permit application from Harbor 1 LLC to conduct work impacting the Columbia River at River Mile 108.4 in Portland, Multnomah County, Oregon.
1 years 272 days ago

NWP-2016-22

Margaret Chang is the Regulatory point-of-contact for this permit application from the Port of Kalama to conduct work impacting the Willamette River at approximately river mile (RM) 75.2. in Kalama, Cowlitz County, Washington.
1 years 272 days ago

NWP-2016-283

Margaret Chang is the Regulatory point-of-contact for this permit application from Ross Island Sand and Gravel Co. to conduct work impacting Ross Island Lagoon at approximately river mile 15 of the Willamette River in Portland, Multnomah County, Oregon.
1 years 278 days ago

NWP-2016-151

Danielle Erb is the Regulatory point-of-contact for this permit application from Adam Svenson to conduct work impacting a 1.04 acre wetland in Warrenton, Clatsop County, Oregon.
1 years 294 days ago

NWP-2016-30

Michael LaDouceur is the Regulatory point-of-contact for this permit application from Northwest Aggregates Co. to conduct work impacting the Columbia River between River Miles 80 and 120.
1 years 301 days ago

NWP-2016-410

Michael LaDouceur is the Regulatory point-of-contact for this permit application from Noyes Development Co. to conduct work impacting one wetland, an ephemeral stream, and two roadside ditches in Portland, Oregon.
1 years 313 days ago

NWP-2016-112

Tyler Krug is the Regulatory point-of-contact for this permit application from Gina Dearth to conduct work impacting the Coquille River at River Mile 0.8, in Bandon, Oregon.
1 years 320 days ago

NWP-2008-472-1

Danielle Erb is the Regulatory point-of-contact for this permit application from the Port of Chinook to conduct maintenance dredging in the Port of Chinook, Chinook Washington.
1 years 327 days ago

NWP-2016-264

Carrie Bond is the Regulatory point-of-contact for this permit application from The Oregon Department of Transportation to conduct work impacting Antelope Creek and 14 wetlands (Wetlands A through N) present within the project area in Lakeview, Lake County, Oregon.
1 years 329 days ago

NWP-2014-307-1

Benny Dean is the Regulatory point-of-contact for this permit application from Kent Aldrich to conduct work impacting wetlands and two unnamed tributaries in Monroe, Oregon.
1 years 334 days ago

NWP-2016-57

Brad Johnson is the Regulatory point-of-contact for this permit application from the Bonneville Power Administration to conduct work impacting wetlands in Polk, Marion, Linn and Benton counties in Oregon.
1 years 334 days ago

NWP-2015-402

Judy Linton is the Regulatory point-of-contact for this proposed Regional General Permit authorizing certain maintenance activities in waters of the U.S. within Douglas, Coos and Curry counties. The proposed RGP would be applicable along the South Coast of Oregon from the Umpqua River in Douglas County to the California border and within the limits of Oregon’s designated coastal zone.
1 years 336 days ago

NWP-2016-127

Michael LaDouceur is the Regulatory point-of-contact for this permit application from Polygon NW Company to conduct work impacting a tributary to the Tualatin River and associated wetlands in Tigard, Oregon.
1 years 336 days ago

NWP-2010-593-2

Carrie Bond is the Regulatory point-of-contact for this permit application from the Oregon Department of Transportation to conduct work impacting Whetstone Creek, North and South Swanson Creek, ditches, and associated wetlands in Medford, Oregon.
1 years 336 days ago

NWP-2015-186

Tyler Krug is the Regulatory point-of-contact for this permit application from The Oregon Department of Fish and Wildlife to conduct work impacting Wetlands abutting and adjacent to unnamed tributaries to Sevenmile Creek, and channels abutting Beaver Slough in Bandon, Coos County, Oregon.
1 years 341 days ago

NWP-2016-180

Andrea Wagner is the Regulatory point-of-contact for this permit application from the Albany Parks Department to conduct work impacting an unnamed wetland adjacent to municipal stormwater pipes in Albany, Linn County, Oregon.
1 years 344 days ago

NWP-2015-436

Omar Ortiz is the Regulatory point-of-contact for this permit application from Pacific Power to conduct work impacting 4.78 acres of wetlands and a roadside ditch in Central Point, Jackson County, Oregon.
1 years 356 days ago

NWP-1997-200-4

Tyler Krug is the Regulatory point-of-contact for this permit application from the Curry County Road Department to conduct work impacting Hunter Creek near Gold Beach, Oregon.
1 years 358 days ago

NWP-2016-240

Benny A. Dean, Jr. is the Regulatory point-of-contact for this permit application from Circle Drive Partners, LLC to conduct work impacting approximately 22.87 acres of wetlands and two unnamed tributaries to Oak Creek in Corvallis, Oregon.
1 years 362 days ago

NWP-2016-128

Danielle Erb is the Regulatory point-of-contact for this permit application from Adam Crites to conduct work impacting the Alder Creek, Spruce Forested Wetland, Scrub/Shrub Wetland and Red Alder Forested Wetland in Warrenton, Oregon.
2 years 18 days ago

NWP-2007-729-2

Danielle Erb is the Regulatory point-of-contact for this permit application from Warrenton Fiber Company to conduct work impacting the Columbia River at River Mile 10.2, in Warrenton, Oregon.
2 years 27 days ago

NWP-2016-289

Brad Johnson is the Regulatory point-of-contact for this permit application from the Port of Garibaldi to conduct work impacting Tillamook Bay.
2 years 27 days ago

NWP-2010-535

Anita Andazola is the Regulatory point-of-contact for this permit application from the City of Prineville to conduct work impacting wetlands wetlands adjacent to the Crooked River and approximately 1.5 miles of the Crooked River from river mile 44.5 to 46, in Crook County, Oregon.
2 years 27 days ago

NWP-2016-147

Peter Olmstead is the Regulatory point-of-contact for this permit application from Idaho Power Company to conduct work impacting the Snake River at river mile 333.0, in Huntington, Oregon.
2 years 32 days ago

NWP-2014-92-2

Tyler Krug is the Regulatory point-of-contact for this permit application from the Oregon Department of Fish and Wildlife to conduct work impacting Beaver Slough near Coquille, Oregon.
2 years 41 days ago

NWP-2011-314-2

Melody White is the Regulatory point-of-contact for this permit application from McCall Oil and Chemical Corporation to conduct work impacting the Willamette River at river mile 8.0, in Portland, Oregon.
2 years 45 days ago

NWP-2016-130

Anita Andazola is the Regulatory point-of-contact for this permit application from Key Line Construction to conduct work impacting the North Fork Roberts Creek in Roseburg, Oregon.
2 years 57 days ago

NWP-2014-37-2

Melody White is the Regulatory point-of-contact for this permit application from Stern Group LLC, to conduct work impacting the Columbia River, river mile 108.6, in Portland, Oregon.
2 years 89 days ago

NWP-1996-1035-3

Tyler Krug is the Regulatory point-of-contact for this permit application from Thomas Leith to conduct work impacting Hunter Creek in Gold Beach, Oregon.
2 years 118 days ago

NWP-2014-383-1

Heidi Firstencel is the Regulatory point-of-contact for this permit application from Georgia 01, LLC, to conduct work impacting an unnamed tributary to Muddy Creek in Coburg, Oregon.
2 years 124 days ago

NWP-2010-540-1

Michael LaDouceur is the Regulatory point-of-contact for this permit application from the Portland Development Commission to conduct work over the Willamette River at river mile 11.3, in Portland, Oregon.
2 years 126 days ago

NWP-2012-181-1

Dominic Yballe is the Regulatory point-of-contact for this permit application from the Clackamas County Development Agency to conduct work impacting wetlands near the Clackamas River in Happy Valley, Oregon.
2 years 129 days ago

NWP-2015-483

Heidi Firstencel is the Regulatory point-of-contact for this permit application from GTO Property, LLC, to conduct work impacting wetlands at a site near W. 11th Avenue and Westec Drive in Eugene, Oregon.
2 years 133 days ago

NWP-2015-432

Peter Olmstead is the Regulatory point-of-contact for this permit application from the city of Halfway to conduct work impacting wetlands adjacent to Pine Creek and an unnamed tributary; wetlands adjacent to Lee Creek; and wetlands adjacent to an unnamed tributary of Sag Creek, in the city of Halfway, Oregon.
2 years 136 days ago

NWP-2010-593-1

Carrie Bond is the Regulatory point-of-contact for this permit application from the U.S. Department of Transportation to conduct work impacting Lithia Mitigation Site Wetlands, Lithia Log Pond, Wetland I and Vernal Pool Complex, Medford, Oregon.
2 years 136 days ago

NWP-2016-45

Andrea Wagner is the Regulatory point-of-contact for this permit application from the city of Albany to conduct work impacting unnamed tributaries to and wetlands abutting the Albany Canal, Albany, Oregon.
2 years 138 days ago

NWP-2015-160

Anita Andazola is the Regulatory point-of-contact for this permit application from PC Roseburg, LLC, to conduct work impacting Wetlands abutting Newton Creek in Roseburg, Oregon.
2 years 145 days ago

NWP-1998-668-1

Anita Andazola is the Regulatory point-of-contact for this application for a permit from Fugate Farms, LLC, to conduct work impacting wetlands adjacent to Twomile Creek in Bandon, Oregon.
2 years 152 days ago

NWP-2006-808-3

Tyler Krug is the Regulatory point-of-contact for this permit application from Roguejets, Inc., to conduct work impacting multiple sites in the Rogue River from Gold Beach to Agness, Oregon.
2 years 165 days ago

NWP-2015-453

Brad Johnson is the Regulatory point-of-contact for this permit application from the Port of Alsea to conduct work impacting Alsea Bay in Waldport, Oregon.
2 years 171 days ago

NWP-2016-27

Brad Johnson is the Regulatory point-of-contact for this permit application from Portland General Electric to conduct work impacting the Clackamas River at River Mill Dam in Estacada, Oregon.
2 years 172 days ago

NWP-1999-853-6

Brad Johnson is the Regulatory point-of-contact for this permit application from the Rose City Yacht Club to conduct work impacting the south bank of the Columbia River, River Mile 109.1, adjacent to 3737 NE Marine Drive in Portland, Oregon.
2 years 172 days ago

NWP-2005-426

Melody White is the Regulatory point-of-contact for this application for a permit from the Port of Portland to conduct work adjacent to Terminals 2, 4, 5 and 6, Berths 308 and 315, and the Navigation Facility in Portland, Oregon.
2 years 185 days ago

NWP-2014-347

Michael LaDouceur is the Regulatory point-of-contact for this application for a permit from Suttle Road Moorage, LLC, to conduct work impacting the Oregon Slough portion of the Columbia River at River Mile 2.6 in Portland, Oregon.
2 years 200 days ago

NWP-2015-502

Andrea Wagner is the Regulatory point-of-contact for this application for a permit from Hudson Capital/MBBH Development, LLC, to conduct work impacting wetlands abutting Traux Creek in Albany, Oregon.
2 years 200 days ago

NWP-2004-78-5

Danielle Erb is the Regulatory point-of-contact for a permit application from the Port of Ilwaco to conduct work impacting the north shoreline of Baker Bay, Ilwaco, Washington.
2 years 207 days ago

NWP-2015-518

Michael LaDouceur is the Regulatory point-of-contact for this application for a permit from Robert Evans Company, Inc., to conduct work impacting wetlands on property located at the intersection of NW Five Oaks Drive and NW Croeni Road near Hillsboro, Oregon.
2 years 207 days ago

NWP-1994-565/7

Anita Andazola is the Regulatory point-of-contact for this application for a permit from Salmon Harbor Marina to conduct work in Winchester Bay, Ore.
2 years 208 days ago

Emergency Procedures

The U.S. Army Corps of Engineers (Corps), Portland District, Regulatory Branch is providing the following emergency permitting procedures to the public:
2 years 210 days ago

NWP-2000-320-3

Benny Dean, Jr. is the Regulatory point-of-contact for this application for a permit from GPA1 LLC, to conduct work impacting some unnamed wetlands and tributaries Corvallis, Oregon.
2 years 221 days ago

NWP-2015-479

Danielle Erb is the Regulatory point-of-contact for this application for a permit from Port Warren Moorage Association to conduct work impacting the Skipanon River at river mile 1.2 in Warrenton, Oregon.
2 years 241 days ago

NWP-2015-480

Danielle Erb is the Regulatory point-of-contact for this application for a permit from Charlton Deep Sea Charters, Inc. to conduct work impacting the Skipanon River at river mile 1.2 in Warrenton, Oregon.
2 years 241 days ago

NWP-2015-391

Tyler Krug is the Regulatory point-of-contact for this application for a permit from the Oregon International Port of Coos Bay to conduct work impacting South Slough, Joe Ney Slough and Coos Bay, Charleston, Oregon.
2 years 243 days ago

NWP-2008-226-3

Benny Dean is the Regulatory point-of-contact for this application for a permit from the city of Corvallis to conduct work impacting wetlands and waterway features which flow to the Marys River near Corvallis, Oregon.
2 years 255 days ago

NWP-2008-728-3

Brad Johnson is the Regulatory point-of-contact for this application for a permit from the city of Lincoln City to conduct work impacting the D-River in Lincoln City, Oregon.
2 years 259 days ago

NWP- 2015-252

Kinsey Friesen is the Regulatory point-of-contact for this application for a permit from Montagne Development Inc. to conduct work impacting some wetlands associated with South Fork Ash Creek, in Independence, Oregon.
2 years 277 days ago

NWP-2014-310

Kinsey Friesen is the Regulatory point-of-contact for this application for a permit from Hollis Land and Timber to conduct work impacting an unnamed tributary to Bryan Creek in Newberg, Oregon.
2 years 277 days ago

NWP-1999-381/4

Tyler Krug is the Regulatory point-of-contact for this application for a permit from the Port of Brookings-Harbor to conduct work impacting the Chetco River, mile 0.4, and within the Pacific Ocean near Harbor, Oregon.
2 years 278 days ago

NWP-2014-177-2 and NWP-2015-111

Melody White is the Regulatory point-of-contact for two permit applications for related projects from the Port of Kalama and Northwest Pipeline, LLC, to conduct work impacting the Columbia River near Kalama, Washington.
2 years 283 days ago

NWP-2011-522-2

Andrea Wagner is the Regulatory point-of-contact for this application for a permit from Selmet, Inc., to conduct work impacting some wetlands and waterways in Albany, Oregon.
2 years 292 days ago

NWP-2015-392

Danielle Erb is the Regulatory point-of-contact for this application for a permit from TC Tigard, LLC, to conduct work impacting wetlands associated with an unnamed tributary to Fanno Creek, Tigard, Oregon.
2 years 294 days ago

NWP-2015-206

Heidi Firstencel is the Regulatory point-of-contact for this application for a permit from Seneca Sawmill Company to conduct work impacting wetlands and unnamed tributaries in the Amazon Creek watershed in Eugene, Oregon.
2 years 297 days ago

NWP-2015-322

Kinsey Friesen is the Regulatory point-of-contact for this application for a permit from Riverbend Landfill Company to increase the size of its existing municipal solid waste landfill on land owned by the landfill in McMinnville, Oregon.
2 years 314 days ago

NWP-2006-6

Carrie Bond is the Regulatory point-of-contact for this application for a permit from the Oregon Department of Transportation to conduct work impacting waterways within the Cougar Creek main stem, Crystal Creek main stem, and Eddy Creek Tributary C, along Highway 20 in Eddyville, Oregon.
2 years 319 days ago

NWP-1995-847-1

Kinsey Friesen is the Regulatory point-of-contact for this application for a permit from J.C. Compton Company to conduct work impacting wetlands adjacent adjacent to Turner Lake in Turner, Oregon.
2 years 319 days ago

NWP-2008-224-1

Heidi Firstencel is the Regulatory point-of-contact for this application for a permit from Lane County School District No. 4J to conduct work impacting wetlands adjacent to a tributary to Amazon Creek in Eugene, Oregon.
2 years 326 days ago

NWP-2013-141/1

Heidi Firstencel is the Regulatory point-of-contact for this application for a permit from McDougal Brothers, Inc., to conduct work impacting wetlands adjacent to Amazon Diversion Canal/Amazon Creek in Eugene, Oregon.
2 years 335 days ago

NWP-2014-276

Tom Taylor is the Regulatory point-of-contact for this proposal establish a 66.43-acre wetland mitigation project in Tillamook County, Oregon.
2 years 355 days ago

NWP-2013-292

Dominic Yballe is the Regulatory point-of-contact for this application for a permit from Port of Tillamook Bay to conduct work impacting affect various tidal and non-tidal features contributing waters to Tillamook Bay, Tillamook County, Oregon.
2 years 360 days ago

NWP-2015-234

Tom Taylor is the Regulatory point-of-contact for this proposal establish a 47.3-acre wetland mitigation project in Warrenton, Oregon.
2 years 360 days ago

NWP-2014-165

Richard Chong is the Regulatory point of contact for this application for a permit from Saddle Mountain, Inc., to conduct work impacting the Skipanon and Columbia rivers in Warrenton, Oregon.
3 years 3 days ago

NWP-2007-1005-1

Judy Linton is the Regulatory point-of-contact for this proposal to reauthorize Regional General Permit 5, Discharges into Vernal Pool Wetlands, in Jackson County, Oregon.
3 years 11 days ago

NWP-2006-923-1

Tyler Krug is the Regulatory point-of-contact for this application for a permit from Freeman Rock, Inc., to conduct work impacting the Rogue River, River Mile 2.8 near Gold Beach, Oregon.
3 years 30 days ago

NWP-2015-170

Andrea Wagner is the Regulatory point-of-contact for this application for a permit from Mennonite Homes of Albany, Inc., to conduct work impacting wetlands adjacent to Oak Creek in Albany, Oregon.
3 years 46 days ago

NWP-2015-38

Melody White is the Regulatory point-of-contact for this application for a permit from Front St. Marine, LLC, to conduct work impacting Yaquina Bay and the Yaquina River in Newport, Oregon.
3 years 52 days ago

NWP-2013-172

Jaimee Davis is the Regulatory point-of-contact for this application for a permit from the U.S. Coast Guard to dredge less than one acre portion of an existing berth area in the Swan Island Lagoon, Portland, Oregon.
3 years 54 days ago

NWP-2015-129

Melody White is the Regulatory point-of-contact for this application for a permit from Riverside Homes, LLC, for work impacting less than one acre of wetland in the Beaverton Creek watershed, Beaverton, Oregon.
3 years 61 days ago

NWP-2014-142

Kinsey Friesen is the Regulatory point-of-contact for this application for a permit from R4 Sons, LLC, for work impacting two wetlands in Salem, Oregon.
3 years 82 days ago

NWP-2005-480-1

Benny Dean is the Regulatory point-of-contact for this application for a permit from Hayden Homes for work impacting less than one acre of wetlands in Springfield, Oregon.
3 years 90 days ago

NWP-2004-464-2

Tyler Krug is the Regulatory point-of-contact for this application to modify a permit from the Port of Port Orford for work impacting the federal navigation channel near the city of Port Orford, Oregon.
3 years 93 days ago

NWP-2002-40-4

Carol Franson is the Regulatory point-of-contact for this permit application from Fred Wahl Marine Construction, Inc., for work impacting the Umpqua River Estuary in Reedsport, Oregon.
3 years 96 days ago

NWP-2008-226-2

Omar Ortiz is the Regulatory point-of-contact for this permit application from the city of Corvallis Public Works Transportation Division for work permanently impacting wetlands adjacent to an unnamed tributary to Lower Marys River near Corvallis, Oregon.
3 years 96 days ago

NWP-2015-91

Michael LaDouceur is the Regulatory point-of-contact for this permit application from West Hills Development for work permanently impacting wetlands the North Bethany community near Beaverton, Oregon.
3 years 111 days ago

NWP-2011-522-1

Andrea Wagner is the Regulatory point-of-contact for this permit application from Selmet, Inc., for work impacting 3.23 acres of wetlands and waterway in Albany, Oregon.
3 years 123 days ago

NWP-2014-43

Michael LaDouceur is the Regulatory point-of-contact for this permit application from Tri-County Center Trust for work impacting some wetlands and an unnamed tributary to Red Rock Creek in Tigard, Oregon.
3 years 129 days ago

NWP-2002-183-2

Carol Franson is the Regulatory point-of-contact for this permit application from Mr. Howard and Ms. Sharon Dickerson for work impacting the North Umpqua River in Roseburg, Oregon.
3 years 130 days ago

NWP-2007-125-1

Michael LaDouceur is the Regulatory point-of-contact for this permit application from Alan DeHarpport, LWD, LLC, for work impacting a wetland in Hillsboro, Oregon.
3 years 132 days ago

NWP-2015-71

Michael LaDouceur is the Regulatory point-of-contact for this permit application from the Beaverton School District for work in the South Cooper Mountain area, in Beaverton, Oregon.
3 years 132 days ago

NWP-2011-465

Steve Gagnon is the Regulatory point-of-contact for this Special Public Notice regarding the establishment of a Danger Zone at the Oregon National Guard Base at Camp Rilea, Ore.
3 years 146 days ago

NWP-2014-446

Michael LaDouceur is the Regulatory point-of-contact for this permit application from the city of Hillsboro for work in the Tualatin River at river mile 39.4, in Hillboro, Ore.
3 years 146 days ago

NWP-2015-043

Benny Dean Jr. is the Regulatory point-of-contact for this permit application from Lane County Public Works for work impacting approximately 1.72 acres of wetlands in Eugene, Ore.
3 years 159 days ago

NWP-2014-424

Omar Ortiz is the Regulatory point-of-contact for this permit application from Oliver Spires for work in unnamed tributaries and wetlands adjacent to Lower Crooked Creek, in Lakeview, Ore.
3 years 165 days ago

NWP-2008-694-1

Andrea Wagner is the Regulatory point-of-contact for this permit application from Eugene Freezing and Storage Co. for work in wetlands adjacent to Beaver and Oak creeks in Albany, Ore.
3 years 177 days ago

NWP-2014-200

Michael LaDouceur is the Regulatory point-of-contact for this permit application from Venture Properties for work in the Fanno Creek watershed in Tigard, Ore.
3 years 180 days ago

NWP-2013-70-1

Danielle Erb is the Regulatory point-of-contact for this permit application from Meisel Rock Products for work on the Weston Bar at River Mile 60 of the Willamette River, near Dayton, Ore.
3 years 188 days ago

NWP-2007-551/1

Joseph Sheahan is the Regulatory point-of-contact for this permit application from the Cedar Investment Group for work impacting wetlands adjacent to and abutting drainage and Lone Pine Creek in Medford, Oregon.
3 years 192 days ago

NWP-2005-748

The U.S. Army Corps of Engineers, in coordination with the Oregon Department of Environmental Quality, is holding two public information meetings to explain the evaluation process for the Oregon LNG terminal and pipeline. The public is invited to attend and ask agency representatives process-related questions to learn more about how permit applications are reviewed by the Corps, DEQ and other agencies.
3 years 192 days ago

NWP-2012-441

The U.S. Army Corps of Engineers, in coordination with the Oregon Department of Environmental Quality, is holding four public information meetings to explain the evaluation process for the Jordan Cove Energy Project LNG terminal and pipeline. The public is invited to attend and ask agency representatives process-related questions to learn more about how permit applications are reviewed by the Corps, DEQ and the Oregon Department of Land Conservation and Development.
3 years 194 days ago

NWP-2008-188

Carrie Bond is the Regulatory point-of-contact for this permit application from the Oregon Dept. of Transportation, Region 3, for work impacting an unnamed tribuary to Tolman Creek and adjacent wetlands, in Ashland, Ore.
3 years 214 days ago

NWP-2014-469

Joseph Sheahan is the Regulatory point-of-contact for this permit application from the Geos Institute for work impacting Evans Creek 10.3 miles upstream from the confluence with the Rogue River by breaching Wimer Dam.
3 years 221 days ago