Home > Missions > Current projects > Bradford Island

Bradford Island

Until about 1982, the landfill on Bradford Island was used to dispose of project waste materials like oil and grease, paint and solvents, scrap metals, mercury-vapor lamps, cables and sandblast grit. Some electrical transmission components like switchgear, insulators and possibly light ballasts were also in the landfill. Household waste came from a small community of homes used by construction workers and later project personnel until 1976. The total landfill area is about a half acre in size (about one-third of a football field in area), and is estimated to hold about 8,800 cubic yards of material, including soil used to fill and cover the landfill. It is on the northeastern portion of Bradford Island, and is not in a public area.

The sandblast building was used for sandblasting and painting from about 1958 to 1995. The area impacted by sandblast grit includes the sandblast area and the transformer release area. A burn pit located southeast of the sandblast building and a septic system, not currently in use, northwest of the building are additional potential sources of contamination within the sandblast area. In addition, an area of previously unknown contamination was discovered in the course of soil sampling. Findings of a 2006 investigation conclude that the area contains an estimated 1500 cubic yards of contaminated material.

A small area, approximately 95 cubic yards, on the south side of the island was used for small arms target practice through the 1970s. Lead concentrations have been detected.

Hydrographic and underwater dive surveys in late 2000 led to the discovery of light ballasts on the Bulb Slope area off Bradford Island, impacting an area estimated at 100 cubic yards. Mercury is present, but the sediment has not been greatly impacted. The dive survey also revealed power transmission components containing significant levels of PCBs.

For more information

Phone: 503-808-4510

Email us about Bradford Island

Latest News Releases

About this project

Collapse All Expand All

  Portland District released a draft report in late December 2010 that documents our investigation; identifies the sources, nature and extent of the remaining environmental contamination; and identifies potential concerns to human health and the environment.

  The report concludes that contaminants both on land and in the water exceed risk screening levels, and proposes that we perform a feasibility study of the in-water area to identify remedial actions that will lower concentrations to an acceptable risk level.  It also proposes that we perform either a feasibility study of the land areas or a site-specific baseline Human Health Risk Assessment or Level III Ecological Risk Assessment to determine if risks to human health or ecological receptors are unacceptable.

In the late 1980s and early 1990s, the Corps began efforts to bring Bonneville Lock and Dam into compliance with new hazardous waste regulations.  The Corps during that time was also developing the Environmental Review Guide for Operations program. ERGO is a comprehensive self-evaluation and program management system for achieving, maintaining and monitoring compliance with environmental laws and regulations at Corps of Engineers projects and facilities.

  • 1990: The ERGO program was given a pilot test.
  • 1991: Portland District's ERGO program became operational.
  • 1992: The first internal ERGO audit of the Bonneville project was held.
  • 1995: Retired and current employees were interviewed about the landfill.
  • 1996: Contaminants were confirmed in the landfill and letters were sent to the Environmental Protection Agency and the Oregon Department of Environmental Quality, notifying of CERCLA release.
  • 1997: The Corps signed a Voluntary Cleanup Agreement with the Oregon DEQ.
  • 1998: The Corps conducted a landfill site investigation.
  • 2000: An underwater dive survey discovered equipment containing PCBs.
  • 2002: Divers removed in-water electrical equipment.
  • 2002: Specialists conducted a preliminary assessment and inspection of the sandblast area.
  • 2003: Divers collected samples of in-water sediments and clams.
  • 2004: The Corps completed an ecological and human health risk assessment.
  • 2005: The Corps did a draft engineering evaluation and cost analysis for landfill and in-water areas.
  • 2006: Divers conducted additional fish sampling.

2007: The Corps removed 65 tons of sediment from an 0.83-acre area along the shoreline of Bradford Island.  2.2 million gallons of water and sediment were suctioned from the river bottom and filtered to remove contaminants.  The resulting filtered water that was returned to the river was non-detectable for PCBs at five parts per trillion.  The captured sediment that was taken to a licensed landfill was non-detectable for PCBs at 80 parts per billion.  The sediment results seem to indicate that the average contamination level in the river was far lower than originally estimated.

 

This information was last updated Dec. 6, 2011.  

The Corps continues to work with state and tribal health agencies to inform area anglers about the danger of eating contaminated fish.